Fort St. Vrain in Pictures: 5

March 29, 2018, 11:00AMANS Nuclear Cafe

In the last half of 1968, Public Service of Colorado obtained the necessary approvals from the US Atomic Energy Commission and from the Colorado Public Service Commission to begin the actual construction of its Fort St. Vrain Nuclear Generating Station.

Fort St Vrain Model second viewAbove, the design developed for the Fort St. Vrain station is again represented in model form.  The reactor building is nearest, with the reactor core itself visible as a dark half-cutaway cylinder in the center of the heavy prestressed concrete reactor vessel or PCRV.  The turbine building stretches out to the right of the photo, with administrative and staff facilities built out in front connected to the road by the sidewalk visible on the model.

Aerial photo showing site preparation underway for the Fort St. Vrain Nuclear Generating Station.

In the view above, County Road 19-1/2 cuts through the photo from the lower center to the right; we are looking roughly East here from the air.  The plant's site can be seen as the area near the center of the photo where a rough oval appears; this is the location of an ice wall constructed to hold back ground water encountered on the drive down to bedrock.  A creek runs along the site, which is visible as a dark line near the right middle of the photo.  Two spurs from the Union Pacific railroad enter the site from the West.

Fort St Vrain circ water pipes under turbine foundation

Original caption:  "Circulating water lines are installed in turbine building foundations at Fort St. Vrain Nuclear Generating Station.  Steel pipes, nearly seven feet in diameter, carry water between steam condenser and cooling tower for 330,000 kilowatt plant Gulf General Atomic is building for Public Service Company of Colorado."

Fort St Vrain welding lower head

Original caption:  "Welding shield encircles bottom head liner for Fort St. Vrain Nuclear Generating Station's prestressed concrete reactor vessel.  Finished steel liner is being fabricated at the plant site and later will be moved into the reactor building.  Holes are penetrations for helium coolant circulators and steam generators.  Gulf General Atomic is prime contractor to Public Service Company of Colorado for the 330,000 kilowatt nuclear plant."

(Although General Atomic - who was bought from General Dynamics by Gulf Oil in 1967 - was the prime contractor for the plant and point of contact for the owner, Public Service of Colorado, it did not work alone.  GA hired Sargent & Lundy as architect-engineer for the project, and hired EBASCO Services as constructor.)

The specific piece seen above is the lowest steel component that will sit inside the PCRV cavity.  The circular openings around the edge are for the 12 steam generator modules; the four inner ones are for the helium circulators, and the central opening is the manway access to the lower PCRV area for inspection and maintenance.  Workers standing on the lower head liner give sense of scale.

Fort St Vrain lower head assembly

Reactor vessel's bottom head assembly before placement in lower portion of reactor building, as shown in Fort St. Vrain brochure.

The March 1969 PSCo "News Briefs" flyer featured two interesting photos of the plant's construction progress and gave the following information (in italics.)

"Aerial view of the bottom head assembly before it was lowered into final position."

"Aerial view of the bottom head assembly before it was lowered into final position."

"Bottom of Reactor Vessel Placed at Fort St. Vrain:  The huge bottom head assembly was placed into its final position at the Fort St. Vrain Nuclear Generating Station on Friday, February 21.  The 400 ton piece of equipment, which is the lower portion of the vessel which will contain the plant's nuclear fuel, had to be moved some 200 feet horizontally from its point of fabrication into position above its supporting foundation.  From that point, it was lowered 20 feet into final position on the foundation.  

The 48-foot diameter assembly stands some 60 feet high.  It was moved horizontally by a gantry crane.  The gantry traveled along steel rails, pulled by steel cables attached to a 150-ton crane that provided the motive power.  Jacks on the gantry crane lowered the assembly into its foundation.  

Substantial headway is being made at Fort St. Vrain.  In addition to the fabrication and placing of the bottom head assembly, considerable progress has been made upon foundations for the reactor and turbine buildings, and the placing of the concrete for the pedestal upon which the plant's turbine generator will be placed. 

Approximately 500 men are at work at the plant site, four miles northwest of Platteville.  Fort St. Vrain is expected to go into operation in 1972."

"Aerial view of turbine - generator pedestal under construction for the Fort St. Vrain plant."

"Aerial view of turbine - generator pedestal under construction for the Fort St. Vrain plant."

Fort St Vrain placing last steel

The photo above shows the placement of a US flag erected on the reactor building at the time of the placement of the last, highest structural steel.  The construction of the reactor building was completed in April 1969, as was the construction of the turbine generator pedestal.  However, much work remained to be done and by June 1, 1969 the contractors considered the project 28% complete; this level of completion was attained in roughly eight months.

Fort St Vrain across waterFort St. Vrain, like many other plants of its day, would not meet its original schedule.  The plant was essentially complete and ready for hot testing in 1972 but was not granted an operating license by the Atomic Energy Commission until December 1973.  Many hurdles would have to be overcome during the unfortunately and unexpectedly protracted run up to commercial operation, but many of these were overcome.  In our next and final installment we'll take a look at the plant's operational history and provide some historical perspective.

Will DavisWill Davis is a member of the Board of Directors for the N/S Savannah Association, Inc. He is a consultant to the Global America Business Institute, a contributing author for Fuel Cycle Week, and he writes his own popular blog Atomic Power Review. Davis is also a consultant and writer for the American Nuclear Society, and serves on the ANS Communications Committee and the Book Publishing Committee. He is a former U.S. Navy reactor operator and served on SSBN-641, USS Simon Bolivar.  His popular Twitter account is @atomicnews

 

Feel free to leave a constructive remark or question for the author in the comment section below.